Project charter template

A project charter is the short document that starts a project. It says why the project exists, what it must achieve, what's in and out of scope, who the sponsor is, how success will be measured and what limits it must work within. Once the sponsor signs it, the project manager has the authority to spend time and money on the work. This free Word template fits on two or three pages.

Download the Word template

Word (.docx) · 38 KB · free, no sign-up

Running a company of 30 to 200 people? Documents like this are now worth money.

It comes before the detailed project plan, and its job is to get the people who fund and run the project agreeing before anyone works out tasks and dates.

What's in the template

Project charter

Project name 
SponsorOwns the outcome and the budget
Project manager 
Prepared on 
Version 
Decision needed by 

1. Purpose

The problem or opportunity in two or three sentences, and what happens if we do nothing.

2. Objectives and success measures

Objective (a result, not an activity)How we'll knowTargetBy when
    
    
    

3. Scope

IncludedExcludedNot yet decided
   
   
   

4. Main deliverables

What will exist at the end: a system, a building, a trained team, a new way of working.

5. Sponsor, team and stakeholders

Person or groupRole in the projectWhat they need from it
 Sponsor 
 Project manager 
 Team member 
 Affected team or customer 

6. Key dates

MilestoneTarget dateFixed or flexible?
Charter approved  
Project plan approved  
   
Project complete  

7. Budget and resources

Budget limitIncluding contingency
Paid fromBudget or cost centre
People neededWho, and roughly how many days
Outside helpSuppliers, contractors or advisers

8. Constraints, assumptions and known risks

TypeDescriptionEffect if it changes or happens
Constraint  
Constraint  
Assumption  
Risk  

9. Authority

Project manager can decidee.g. spending within budget lines; task dates that don't move a milestone
Sponsor must decideChanges to scope, milestones or the budget
Goes to the board whene.g. the budget limit or the completion date would be exceeded

10. Approval

NameRoleDecisionSignatureDate
 SponsorApproved / not approved  
 Project managerAccepted  
     

Charter or project plan: what's the difference?

They share some headings but answer different questions.

Project charterProject plan
QuestionShould we do this, and on what terms?How exactly will we do it?
WrittenBefore work starts, usually by the project manager with the sponsorAfter the charter is approved, by the project manager with the team
DetailPurpose, objectives, boundaries, limits, authorityTasks, dates, named people, budget lines, risks, communication
ChangesRarely; a big change means the project itself has changedThrough change control as the work goes on

For a small internal project, the charter can be the first page of the plan. Keep the sponsor's signature on it either way.

How to write a project charter

  1. Draft it with the sponsor, not for them. An hour together is usually enough. A sponsor who won't give that hour won't make time for the decisions later.
  2. Describe the problem before the solution. "Paper job sheets are re-typed in the office, so invoices go out late" is a better purpose than "introduce a mobile app", because it leaves room to choose the best fix.
  3. Turn the purpose into two to four objectives, each with a measure, a target and a date. If nobody can say how success will be checked, the project isn't ready.
  4. Draw the boundary. List what's excluded, especially the natural extensions people will assume, and the questions still open.
  5. State the limits: the budget ceiling, any fixed date, and rules such as using existing systems.
  6. Set the project manager's authority and the point where decisions go back to the sponsor. If several teams are involved, agree a RACI matrix at the same time.
  7. Circulate it to everyone named, fix what they question, then get the sponsor's signature.

Example: a charter for a fictional contractor

A summary of the charter for a fictional 140-person heating and air conditioning contractor in Ohio, whose 85 field engineers are moving from paper job sheets to a phone app. It's a US company, so the figures are in dollars.

PurposeOffice staff re-type engineers' paper job sheets, so invoices go out about a week after the work and some sheets are lost. Doing nothing means slower cash and more disputed invoices.
Objectives1. Every job recorded in the app by 30 June. 2. 95% of jobs invoiced within two working days of completion by 30 September. 3. No more admin time for engineers than today, checked by a survey in July.
IncludedThe app for planned and reactive jobs, photos and customer signatures, and the link to the accounting system.
ExcludedScheduling and dispatch (unchanged), van stock, a customer portal.
Not yet decidedWhether subcontractors will use the app.
SponsorOperations director
Limits$75,000 including the first year's software fees; must work offline in basements; live before the autumn heating season.
AuthorityThe project manager can move tasks within a milestone; changes to scope, the June date or the budget go to the sponsor.

Common mistakes

  • Writing it after work has started. Its value is the agreement reached before money is spent.
  • A sponsor in name only: someone too junior to make the calls, or who signs without reading.
  • Objectives that are activities. "Roll out the app" can be done and still fail; "invoices out within two working days" can't.
  • No exclusions, so the scope grows to fit everyone's hopes.
  • No authority section, so the project manager either asks permission for everything or decides things they shouldn't.
  • Turning it into a plan. If it runs past four pages, move the detail into the project plan.

Frequently asked questions

Who signs a project charter?

The sponsor, who takes responsibility for the outcome and the budget. The project manager often signs to accept the role, and for larger spends the managing director or board approves it too.

Is a project charter the same as a business case?

No. A business case argues whether the investment is worth making, with costs, benefits and options. The charter authorises the project and sets its terms. On a small project, a short business case can sit in the purpose section.

Does a small project need a charter?

If it spends real money or needs people from more than one team, a one-page charter is worth the hour. For a few days' work inside one team, an email covering the same points will do.

Can a charter be changed?

Yes, but rarely, and the sponsor should sign the new version. Day-to-day changes to tasks, dates and costs go through the project plan's change control instead.